North West Railway Advances Jaipur-Rewari Corridor

Railway Board sanctions ₹5.73 crore survey for 191-km Jaipur-Rewari line via Neemrana

2026-03-23, Moovit News Team

Jaipur-Rewari Rail Survey Gets ₹5.73 Crore

Railway officials approved a final location survey for a new 191-kilometer rail line connecting Jaipur to Rewari via Neemrana, with ₹5.73 crore sanctioned for the work. The Railway Board's approval marks a significant step toward creating an alternative corridor between Jaipur and Delhi, officials said. The project aims to ease congestion on the existing Jaipur-Delhi route through Alwar-Rewari, which currently experiences heavy traffic pressure and delays.
Survey team examining railway alignment maps and terrain for new Jaipur-Rewari rail corridor through Neemrana industrial area

Industrial Corridor Drives New Route

The proposed track will pass through Neemrana, a crucial hub within the Delhi-Mumbai Industrial Corridor that hosts numerous domestic and international companies. Railway officials said the new connectivity is expected to provide industries with affordable and fast logistics facilities, potentially boosting production and exports in the region. The North Western Railway's General Manager will conduct the survey work, according to the Railway Board. Towns including Kotputli, Shahpura, and Behror have long lacked direct rail connectivity and will benefit from this project.
Industrial facilities and manufacturing units in Neemrana along the Delhi-Mumbai Industrial Corridor awaiting rail connectivity

Survey to Determine Final Alignment

The ₹5.73 crore budget will fund the final location survey to determine the precise alignment of the 191-kilometer route. Officials said the survey will assess terrain, land acquisition requirements, and engineering challenges along the corridor. After the survey is completed, a Detailed Project Report will be prepared and submitted to the Railway Board for approval before construction can commence. Railway officials didn't provide a timeline for when the survey work will begin or how long it will take to complete.

DPR Approval Needed Before Construction

Once the survey work concludes, the North Western Railway will prepare a comprehensive Detailed Project Report outlining construction costs, timelines, and technical specifications. The DPR must receive Railway Board approval before any construction activities can start, officials said. A specific timeline for DPR submission and approval wasn't provided. Railway officials said the project represents a significant step toward strengthening the industrial and transportation infrastructure of the region.

Alternative Route to Ease Congestion

The new line will serve as an alternative corridor between Jaipur and Delhi, offering passengers a new route while reducing travel distance and time. Railway officials said the initiative is expected to foster development, create employment opportunities, and improve overall connectivity in areas that have been underserved by the rail network. Riders can track rail service updates and plan trips using Moovit, which provides real-time information for transit systems across India.