Metro begins 10-month elevator modernization at Glenmont East Parking Garage through July 2026

2026-04-24, Moovit News Team

Metro Starts Glenmont Garage Elevator Work

Metro riders who park at Glenmont station will find one of three elevators out of service in the East Parking Garage through mid-2026. The transit agency started elevator modernization work September 15, 2025, with completion scheduled for July 14, 2026, officials said. Two elevators will remain operational throughout the 10-month project.
Metro elevator undergoing modernization work at Glenmont East Parking Garage with construction barriers and safety signage visible

Context

The modernization is part of Metro's regular elevator maintenance program, which covers more than 350 elevators throughout the system. Transit officials said the agency performs major rehabilitation work every 10-15 years on each elevator, following monthly and annual maintenance schedules. The work aims to improve elevator reliability by replacing and upgrading all major components. Officials didn't specify how many other garage elevators are scheduled for similar work this year.

Details

The project includes installing a new passenger cab, controls, motors, and safety devices, according to Metro. Only one of the garage's three elevators will be out of service at a time, ensuring two remain available for riders. Officials said the work is expected to enhance overall reliability and safety of the elevator system at the Glenmont East Parking Garage. Metro advised customers to stay clear of construction zones and follow all posted signs during the rehabilitation period.

Timeline

Work began September 15, 2025, and continues through July 14, 2026. Officials said two elevators will be available for public use throughout the entire construction period. Metro didn't provide a breakdown of which specific elevator will be rehabilitated first or the timeline for rotating work among the three units.
Metro parking garage elevator entrance with directional signage showing available elevator access during construction

Impact

Riders using the Glenmont East Parking Garage should expect slightly longer waits for elevator access during the modernization work, though two of three elevators will remain operational. Metro said customers can stay informed through MetroAlerts and the MetroPulse app. Moovit provides real-time transit updates and trip planning for Metro riders navigating service changes.