Metro Upgrades Glenmont Elevators While Keeping Access

Metro begins 10-month elevator modernization at Glenmont station parking garage through July 2026

2026-05-04, Moovit News Team

Metro Starts Glenmont Garage Elevator Upgrades

Metro riders who park at Glenmont station will see elevator work underway through mid-2026, though two of three elevators in the East Parking Garage will stay open throughout the project. The transit agency started elevator modernization work at the facility September 15, 2025, with completion scheduled for July 22, 2026, officials said. One elevator will be out of service at a time during the 10-month rehabilitation.
Metro elevator at Glenmont station parking garage with construction barriers and safety signage visible

Context

The modernization is part of Metro's regular elevator maintenance program, which covers more than 350 elevators across the transit system, according to the agency. Metro performs monthly and annual maintenance on all elevators, with major rehabilitation work conducted every 10 to 15 years to extend equipment life and improve reliability. The Glenmont East Parking Garage elevators reached the point where comprehensive upgrades were needed to maintain safe, dependable service for riders accessing the Red Line station.

Details

The project involves replacing and upgrading all major elevator components to improve reliability, transit officials said. New components include a passenger cab, controls, motors, and safety devices. Contractors will rehabilitate each of the three elevators sequentially, ensuring two remain operational at all times for riders who need elevator access from the parking garage to the station platform. Officials advised customers to stay clear of construction zones and follow all posted signs for their safety during the work.

Timeline

Work began September 15, 2025, and will continue through July 22, 2026, according to Metro. The sequential approach means each elevator will be out of service for several months while undergoing rehabilitation, but the staggered schedule ensures riders always have two working elevators available. Officials didn't specify exact timelines for when each individual elevator will be taken out of service and returned to operation.

Impact

Riders who use the East Parking Garage at Glenmont will have continued elevator access throughout the project, with two of three elevators operational at all times. Those who need accessibility accommodations can still reach the station platform from the garage during construction. Metro offers real-time service updates through multiple channels, and riders can check Moovit for current station conditions and alternative parking options if needed during the modernization work.
Modern metro elevator interior showing new control panel, safety features, and accessible design elements