Metro Upgrades Glenmont Elevators for Better Access

Metro modernizes three elevators at Glenmont East Parking Garage through July 2026

2026-04-25, Moovit News Team

Headline

Metro Starts Glenmont Garage Elevator Upgrades

Paragraph 1

Metro riders parking at Glenmont station will find one of three elevators in the East Parking Garage out of service through next summer as the transit agency modernizes the equipment. The rehabilitation work started September 15, 2025, and continues through July 14, 2026, transit officials said. Two elevators will remain operational throughout the project to maintain access for riders who need them.
Elevator bank inside Metro parking garage with modern stainless steel doors and accessibility signage

Paragraph 2

The modernization is part of Metro's regular maintenance program for its fleet of more than 350 elevators across the rail system. Transit agencies typically perform major rehabilitation work every 10-15 years on each elevator to extend equipment life and improve reliability. Metro conducts monthly and annual maintenance on all elevators, but this project involves a complete overhaul of major components. The work aims to reduce breakdowns and improve service for riders who depend on elevators for station access.

Paragraph 3

The rehabilitation includes replacing and upgrading all major elevator components, officials said. New installations include a passenger cab, controls, motors, and safety devices designed to meet current standards. The project tackles one elevator at a time to minimize disruption, with the remaining two elevators handling rider traffic during construction. Metro advised customers to stay clear of construction zones and follow all posted signs for safety throughout the work period.
Metro elevator undergoing modernization with new control panel and safety equipment being installed

Paragraph 4

The project began September 15, 2025, with completion scheduled for July 14, 2026, giving contractors about 10 months to modernize all three elevators sequentially. Metro didn't specify how long each individual elevator will be out of service or the exact rotation schedule for the work. Two elevators will remain available for public use throughout the construction period to maintain accessibility.

Paragraph 5

Riders who regularly use the Glenmont East Parking Garage should plan for potential wait times with reduced elevator capacity during the project. Metro offers multiple ways to stay informed about service changes, including MetroAlerts and the MetroPulse mobile app. Customer Care is available by phone Monday through Friday from 7am to 8pm, and weekends from 8am to 8pm. Moovit provides real-time updates for Metro services to help riders plan trips around construction impacts.